Move furniture as needed to complete the project. Details will be discussed during the Pre-Bid Meeting.
Remove and dispose of existing vinyl composition tile (VCT) and cove base.
Prepare substrate for application of new VCT and cove base.
Install VCT in specified Classrooms and Corridors. Colors to be selected by Owner.
Install cove base. Colors to be selected by Owner.
Work may begin on May 27, 2025, and must be completed by June 27, 2025. Available work hours will be Monday thru Friday, 7am – 3pm. If extended work hours are requested by successful bidder, the contractor must accept full responsibility of opening and/or securing the building.
Work must progress so that the flooring project stays ahead of the summer cleaning project.